The modern public procurement system of Uzbekistan is based on the principles of transparency, competition, and efficiency in the use of budgetary funds. One of the key instruments for ensuring these principles is the tender — a competitive procedure for selecting a public procurement contractor, in which the winner is the participant who offers the most favorable conditions for contract execution.
According to the Law of the Republic of Uzbekistan “On Public Procurement” dated April 22, 2021, No. ZRU-684, a tender is defined as a competition providing for the determination of a contractor through a competitive procedure, as a result of which the winner is recognized as the participant who offered the optimal conditions.
A tender refers to competitive procurement methods (alongside auction, selection of the best proposals, electronic store, etc.) and is aimed at achieving a balance between the price and quality of the procured goods, works, or services.
Principles of Tendering
The tender procedure is regulated by the general principles of public procurement established by the Law:
Participants of Tender Procedures
The key entities are:
Stages of the Tender Procedure
Advantages and Limitations of the Tender Procedure
Advantages:
Limitations:
Tenders as a form of public procurement in Uzbekistan play a key role in ensuring the efficient and transparent use of public funds. Their legal regulation is aimed at attracting the maximum number of participants, improving the quality of procured goods and services, as well as minimizing corruption risks. In the future, further improvement of tender procedures will be associated with the expansion of electronic systems, the introduction of international standards, and increased control by the state and society.
Stages of Tender in Uzbekistan’s Public Procurement
|
Stage |
Content |
Responsible bodies/persons |
Approximate deadlines |
Possible risks |
|
1. Planning |
Inclusion of procurement in annual/quarterly plan-schedule |
Public customer |
By March 25 (annual); by the 25th of the last month of the quarter (quarterly) |
Inaccurate planning; under/overestimation of needs |
|
2. Announcement |
Posting procurement information (subject, price, conditions) |
Public customer via special portal |
20–30 days before application deadline |
Restricted access to info; discriminatory conditions |
|
3. Pre-qualification |
Checking participants’ compliance with criteria (finance, experience, no debts) |
Procurement commission |
Within 5–10 days after applications |
Corruption; exclusion of worthy participants |
|
4. Submission & opening |
Registration and opening of bids (envelopes/e-files) |
Procurement commission (secretary) |
On application deadline day |
Info leakage; breach of confidentiality |
|
5. Evaluation |
Comparison by criteria: price, quality, deadlines, guarantees, eco-friendliness |
Procurement commission, experts (if needed) |
5–15 business days |
Formalism; biased evaluation |
|
6. Winner determination |
Decision by majority vote, protocol |
Procurement commission |
On completion of evaluation |
Collusion; conflict of interest |
|
7. Acceptance |
Official confirmation of winner |
Public customer |
1–3 business days |
Unjustified cancellation |
|
8. Contract conclusion |
Signing contract with winner and registration in Unified Register |
Public customer & winner |
Within 10 business days |
Refusal of winner; delays |
|
9. Contract execution |
Delivery of goods/works/services, payment, supervision |
Contractor & customer |
Depends on contract |
Improper execution; payment delays |
|
10. Monitoring & reporting |
Execution control, publication in register |
Authorized body, customer |
Ongoing |
False reporting; concealment of violations |
Procurement Cases Where Tender Is Not Applicable
The Law “On Public Procurement” of Uzbekistan establishes cases where tenders are not applied, since other forms of procurement or special exceptions are used:
Procurements Allowed and Not Allowed Through Tender
|
Procurement category |
Tender applicability |
Alternative procurement method |
Legal basis |
|
Large procurements of goods, works, services |
Allowed |
Tender |
General norm of procurement law |
|
Technically complex procurements |
Not allowed |
Two-stage procurement |
Art. 4 (definition) |
|
Small-value procurements (up to 50 BCV; for budget — 25 BCV) |
Not allowed |
Simplified procedure |
Art. 30, 51¹ |
|
Standard goods/services of small value (up to 2,500 BCV for budget) |
Not allowed |
E-store |
Arts. 49–51 |
|
Procurements where the only criterion is price |
Not allowed |
Auction (price reduction) |
Art. 4, Art. 30 |
|
Procurements requiring comparison of several offers |
Not allowed |
Selection of best proposals |
Art. 4, Art. 30 |
|
Procurements for defense, security, elections, state secrets |
Not allowed |
Special procedures (closed) |
Art. 2 |
|
Procurement from a sole supplier |
Not allowed |
Direct contract |
Art. 30 |
|
Procurements financed by foreign credits/grants |
Not allowed (if other rules apply) |
Donor/IGO procedures |
Art. 2 |