Subsoil is a strategic national resource, and its use is regulated by special normative acts. In Uzbekistan, the procedure for granting the right to use subsoil plots has been significantly reformed in order to simplify administrative procedures, digitize processes, and create transparent conditions for investors.

The main regulatory act is Resolution of the Cabinet of Ministers No. 133 dated March 25, 2022, which approved the Regulation on the Procedure for Issuing Permits for Subsoil Use. The document details the types of permits, the authorities authorized to issue them, the conditions and terms of validity, as well as the specifics of electronic auctions through the "E-auksion" system.

Types of Permits and Purposes of Use

Permits for subsoil use are issued for various purposes:

  • Geological exploration – search, evaluation, and prospecting of mineral resources;
  • Extraction of minerals – industrial development of deposits;
  • Use of man-made mineral formations – processing of mining industry waste;
  • Construction and operation of underground facilities unrelated to extraction, including storage of hydrocarbons and waste disposal;
  • Creation of protected geological sites;
  • Collection of collectible materials – rare minerals, paleontological finds, etc.

Authorized Bodies

The issuance of permits is carried out by two main authorities:

  • The Ministry of Mining Industry and Geology through the Subsoil Use Center – for most types of use;
  • The Ministry of Ecology, Environmental Protection and Climate Change – for permits related to construction of underground facilities for storage or disposal of waste.

Mechanisms for Granting Permits

Permits may be issued:

  • Through electronic auctions on the "E-auksion" platform;
  • Based on tenders (competitive bidding);
  • On a "first come, first served" basis (including direct negotiations with the authorized body).

An additional benefit for the investor is the "absolute right" – if a company conducts exploration at its own expense and proves reserves, it receives a priority right to obtain a permit for extraction within one year from the date the reserves are approved.

Conditions of Use

Each permit is accompanied by user obligations, including:

  • Fulfillment of the minimum scope of work and investments;
  • Compliance with environmental requirements, including a positive conclusion of the state environmental expertise;
  • Payment of annual license fees, depending on the area of the plot and the type of minerals;
  • Submission of reports on extraction and geological exploration works;
  • Ensuring industrial and environmental safety.

Terms of Permits

  • Geological exploration – up to 5 years;
  • Extraction and use of man-made formations – up to 10 years (with possible extension based on feasibility studies);
  • Collection of collectible materials – up to 2 years;
  • Underground facilities and protected sites – perpetual.

Electronic Auctions "E-auksion"

The auction is a key tool for allocating plots with high commercial potential. The procedure includes:

  • Formation of a list of plots and coordination with sectoral departments;
  • Establishment of the starting price (fixed rates in base calculation units for exploration or a percentage of the estimated value of extraction for exploitation);
  • Conclusion of an agreement with the winner and provision of a full package of geological data.

Financial Aspects

Subsoil users are obliged to pay:

  • Annual license fee – a percentage of the base calculation value per hectare depending on the type of minerals (10% for ore, 15% for non-ore);
  • Taxes and other charges in accordance with the Tax Code;
  • Compensation for land withdrawal for state needs.

Termination or Suspension of Rights

A permit may be restricted, suspended, or revoked in case of violation of conditions, failure to meet obligations, threats to environmental or industrial safety. Temporary conservation of a deposit is also allowed upon notification of the authorized body.

The modern system of granting subsoil use permits in Uzbekistan is aimed at balancing the interests of the state and investors: transparent resource allocation, environmental protection, and stimulation of geological exploration. Full digitalization of processes and transition to electronic auctions significantly reduce bureaucratic barriers and create competitive conditions for business.

 

Requirements and conditions for subsoil use permit holders

No.

Type of Subsoil Use

Main Requirements

Environmental Conditions

Financial Obligations

Term

Other Conditions

1

Geological exploration

- Submission of a preliminary Feasibility Study (term specified in permit);

- Minimum investment volume;

- Work plan approved by the Subsoil Use Center

- Positive conclusion of state environmental expertise (Ecology, Art. 29 a));

- Liquidation/conservation of workings and wells after completion

- Annual license fee: 10% of BCU/ha (Art. 29 a));

- Payment for land allocation preparation services

Up to 5 years (Art. 32 a))

- Submission of reports;

- Transfer of geodata to the state fund

2

Extraction of minerals

- Feasibility study and mining project;

- Minimum investment volume;

- Permits for operation of hazardous facilities

- Positive conclusion of state environmental expertise (Art. 29 b));

- Measures to prevent pollution

- License fee as % of extraction value or fixed rate (Art. 37 b));

- Taxes under Tax Code

Up to 10 years (extendable) (Art. 32 b))

- Local content of works and services;

- Training of local personnel;

- Transfer of rights with consent

3

Use of man-made mineral formations

- Ownership/transfer right for waste;

- Processing project

- Environmental expertise (Art. 29 b));

- Waste control system

- License payment;

- Taxes

Up to 10 years (Art. 32 b))

- May be obtained on "first come, first served" basis

4

Underground facilities unrelated to extraction

- Construction project;

- Positive environmental and geological conclusions

- Determination of permissible storage/disposal volumes (Art. 29 v));

- Sanitary protection zones

- License payment;

- Taxes

Perpetual (Art. 32 g))

- Compensation for possible environmental damage

5

Creation of protected geological sites

- Decision to grant protection status

- Compliance with protection regime

- Exempt from license fees

Perpetual (Art. 32 d))

- Scientific, educational, or tourist purposes

6

Collection of collectible materials

- Purpose: scientific, educational, cultural;

- No mining works

- No violation of subsoil integrity

- License payment (if required)

Up to 2 years (Art. 32 v))

- Ban on collecting samples containing precious metals/gems without a separate permit

 

PROCEDURE FOR OBTAINING A PERMIT FOR GEOLOGICAL EXPLORATION

Stage

Action

Responsible Authorities

Documents & Requirements

Deadlines & Notes

1

Definition of Project Parameters

Define the purpose of works, plot, type of minerals, method of obtaining the right (auction or first-come-first-served)

Applicant

Preliminary plot selection, check in the State Subsoil Cadastre

For strategic and explored plots — auction

2

Preparation of Document Package

Prepare application, attach founding documents, plot map, preliminary feasibility study, work plan, draft application for environmental expertise

Applicant

All documents in state language, electronic format

For underground facilities — separate projects

3

Submission of Application

Submit via “License” portal, EPIGU or “E-auksion”

Applicant, Subsoil Use Center under Ministry of Geology

Electronic registration and submission

For auction — submit within bidding deadlines

4

Auction / Direct Consideration

Participate in auction if plot is listed; if little explored — first-come-first-served review

Subsoil Use Center, “E-auksion”

Guarantee deposit (for auction), participation in bidding

Winner receives auction protocol

5

Obtaining Expert Opinions

Obtain positive state environmental expertise and state expertise of geological materials

Ministry of Ecology, Ministry of Geology

Document package and work project

Mandatory condition before permit issuance

6

Land Lease Agreement

Conclude lease agreement for land plot (free of rent)

Local khokimiyat, Subsoil Use Center

Agreement included in permit conditions

Serves as legal ground for land use

7

Permit Issuance

Receive document indicating plot boundaries, validity (up to 5 years), work conditions

Subsoil Use Center

Work conditions, investment obligations

Permit is official document to start works

8

Payment of License Fees

Pay annual fee per hectare (10% of BCV)

Applicant, Ministry of Finance

Payment documents

70% — to republican budget, 15% — to regional, 15% — to district/city; payment before Feb 1

9

Work Execution

Carry out exploration according to plan, comply with permit conditions

Applicant

Feasibility study, plans, compliance with environmental safety

Minimum investment commitments mandatory

10

Reporting

Submit geological and quarterly reports, transfer geodata to state fund

Applicant, Subsoil Use Center

Reports in established forms

Monitoring compliance with conditions

11

Completion of Works

Conduct reclamation and conservation, agree on closure plan

Applicant, Ministry of Ecology

Reclamation plan, completion report

All materials transferred to the state

12

Extension or Termination

Submit application for extension (if obligations fulfilled) or terminate works

Applicant, Subsoil Use Center

Confirmation of obligations fulfillment

Application filed 60 days before permit expiry

 

PROCEDURE FOR OBTAINING A PERMIT FOR MINERAL EXTRACTION

Stage

Action

Responsible Authorities

Documents & Requirements

Deadlines & Notes

1

Definition of Initial Conditions

Determine type of minerals (strategic or non-ore), select plot, method of obtaining right

Applicant

Preliminary selection, check in State Cadastre

For strategic resources — usually auction/competition

2

Preparation of Document Package

Application, founding documents, feasibility study, mining plan, plot map, industrial & environmental safety docs, draft eco-expertise application

Applicant

All documents in state language, electronic format

Additional approvals if required

3

Submission of Application

Submit via “License” portal, EPIGU or “E-auksion” (if bidding)

Applicant, Subsoil Use Center

Electronic registration and submission

Submit within bidding deadlines

4

Bidding / Direct Provision

Participate in auction/competition or obtain via “absolute right”

Subsoil Use Center, “E-auksion”

Guarantee deposit (for bidding), participation

Winner receives protocol

5

Obtaining Expert Opinions

Positive state eco-expertise and state geological expertise; for hydrocarbons — Ministry of Energy approval

Ministry of Ecology, Ministry of Geology, Ministry of Energy

Document package and work plan

Mandatory condition before permit issuance

6

Land Lease Agreement

Execution of rent-free lease agreement

Local khokimiyat, Subsoil Use Center

Agreement included in permit conditions

Legal basis for land use

7

Permit Issuance

Document indicating term (10 years), plot boundaries, extraction volumes, work conditions

Subsoil Use Center

Investment obligations, rules for associated components

Official document to begin extraction

8

Payment of Fees & Taxes

Payment of extraction rights fees, taxes, subsoil use payments

Applicant, Ministry of Finance

Payment documents

As per legislation

9

Extraction Works

Carry out extraction according to plan, fulfill investment obligations, comply with safety

Applicant

Feasibility study, mining plans, environmental measures

Control over industrial and ecological safety

10

Reporting

Quarterly & annual reports on extraction volumes, associated components, state of subsoil

Applicant, Subsoil Use Center

Reports in established forms

Transfer of data to competent authorities

11

Completion or Conservation

Mine closure/conservation, land reclamation, agree on closure plan

Applicant, Ministry of Ecology

Reclamation plan, completion report

Geological materials transferred to state fund

12

Extension or Termination

Application for extension (if obligations met) or termination

Applicant, Subsoil Use Center

Confirmation of obligations fulfillment

Application filed 60 days before expiry

 

PROCEDURE FOR OBTAINING A PERMIT FOR THE USE OF MAN-MADE MINERAL FORMATIONS (MMF)

Stage

Action

Responsible Authorities

Documents & Requirements

Deadlines & Notes

1

Determining Initial Conditions

Confirm that object qualifies as MMF (mining waste, tailings, etc.), clarify legal status

Applicant

Check in state cadastre, owner data

If object has another user — rights transfer required

2

Choosing Acquisition Method

Choose procedure: auction/competition or direct grant (first-come-first-served)

Applicant, Subsoil Use Center

Direct grant possible only if no owner or via rights transfer agreement

Auction requires registration on “E-auksion”

3

Preparation of Document Package

Application, founding documents, proof of rights to MMF (if any), processing feasibility study, object map, work plan, draft eco-expertise application

Applicant

All documents in state language, electronic format

Additional industrial safety approvals if needed

4

Submission of Application

Through “License” portal, EPIGU or “E-auksion” (if bidding)

Applicant, Subsoil Use Center

Electronic registration and submission

Submit within bidding deadlines

5

Bidding or Direct Grant

Auction/competition to determine winner; direct grant — review of application and transfer of rights

Subsoil Use Center, “E-auksion”

Auction protocol or rights transfer agreement

Winner gets protocol; direct — official decision

6

Obtaining Expert Opinions

State environmental expertise, state geological expertise

Ministry of Ecology, Ministry of Geology

Document package and work plan

Mandatory before permit issuance

7

Land Lease (if required)

Conclusion of rent-free land lease agreement

Local khokimiyat, Subsoil Use Center

Agreement included in permit conditions

Only if land is needed for processing site

8

Permit Issuance

Document indicating term (up to 10 years), processing conditions, environmental & technical requirements, financial obligations

Subsoil Use Center

Investment commitments, processing rules

Gives official right to use MMF

9

Financial Obligations

Payment of license fee, taxes, subsoil use fees (if applicable)

Applicant, Ministry of Finance

Payment documents

As per law

10

Processing Works

Processing of MMF using approved technology, compliance with safety

Applicant

Feasibility study, work plan, environmental measures

Investment commitments mandatory

11

Reporting

Quarterly & annual reports on processing, extracted components, environmental measures

Applicant, Subsoil Use Center

Reports in established forms

Transfer of data to competent authorities

12

Completion of Works

Liquidation/conservation of processing facilities, land reclamation, data transfer

Applicant, Ministry of Ecology

Reclamation plan, completion report

All data transferred to state fund

13

Extension or Termination

Application for extension or termination

Applicant, Subsoil Use Center

Confirmation of obligations fulfillment

Application filed 60 days before expiry

 

Our address
7, Elbek Street, Tashkent city, Uzbekistan
Leave a request
Ask your question
Indicates required fields
Your name:*
Indicates required fields
Your phone:*
Indicates required fields
Your E-mail:*
Indicates required fields
Comments:*
Indicates required fields
Я согласен(а) с обработкой персональных данных*
Спасибо! Ваш запрос отправлен